answer text |
<p> </p><p>The Lightning II aircraft are being procured incrementally. To date the
UK has ordered four F-35 B aircraft, three of which have been delivered. The approved
cost for the production of the four aircraft, including initial spares provision,
risk, concurrency, necessary programme and support arrangements, long lead items and
our contribution to the composite share ratio for the next batch of aircraft is £999
million, as detailed in the National Audit Office Major Projects Report 2013.</p>
|
|